The team at HySeas III are delighted to unveil the schedule for the first stages of practical testing on the project. The main objective is to construct and test a complete hydrogen fuel cell powered ferry propulsion power-train at an onshore test centre in Ågotnes Norway. This setup has been dubbed “the String Test” and should provide a strong insight into how future zero-emission powered ferries could operate in the future. The extended and exhaustive testing over several months is also intended to test safety, load response, transient response, and emergency situations of the system. More details are available at: String Test.
There are several key milestones for the String Test schedule, summarised in the table below, with the start of testing expected to begin in May 2021 and run for approximately 3-4 months. Furthermore, a 3D model of the String Test will be developed such that a virtual walkthrough tour of the site should be possible from anywhere.
Date |
Description |
Summer 2020 |
Introduction of String Test concept and Ågotnes site selection |
Autumn 2020 |
Planning (including detailed safety risk assessment) |
November 2020 |
Construction of housing units for the String Test |
January 2021 |
Installation of battery container, multidrive, AC switchboard, grid transformers, safety, EMS |
January 2021 |
Control room set up |
January 2021 |
Fuel cell container construction |
February 2021 |
Ballard fuel cells shipped and installed |
Spring - Summer 2021 |
Commissioning, component testing |
Autumn 2021 |
String Testing |
Winter 2021/22 |
Completion of testing programme |